Project Overview
Starting in April 2023, the Woburn Sewer Replacement project (EU190) will replace sewer mains in the following areas:
- Woburn Street from Fraser Street south
- Woburn Street from Texas Street to Barkley Boulevard
- Barkley Boulevard from Woburn Street to Newmarket Street
- Yew Street from Carolina Street to Texas Street
Once complete, the impacted areas will be repaved, and all pedestrian ramps made fully ADA accessible.
Project Status – May 2024
Paving is complete and temporary markings will be in place while the asphalt cures. Additional work continues on placing manhole covers and water valve covers; this should be completed by mid-May. Permanent markings will be placed at the end of May/ early June.
Please watch for flaggers and workers.
Construction Impacts
Flaggers will be present. Minor detours may be needed for specific sections of the work. Access to businesses, as well as local access to homes and for emergency vehicles, will be maintained during construction. Construction is expected to conclude in June 2024.
Thank you for your patience.