Broadway and South Hill Sewer Improvements

Project Overview

This project (EU205) will replace or repair aging wastewater mains in the Columbia, Cornwall Park, South Hill, Whatcom Falls, and York neighborhoods through both traditional replacement and cast-in-place pipe relining methods.  

An aging watermain will also be replaced in the Broadway and Whatcom Falls neighborhoods. 

Project Status – Fall 2026

This project is currently under design and outreach. The City’s design consultant, Kimley-Horn is conducting outreach to impacted properties. Construction is planned for late 2027.

Construction Impacts

During construction, there will likely be single-lane road closures and alley closures.

Contact

Media inquiries: pwmedia@cob.org
General questions: askpw@cob.org

Project Engineer:
Joey Malloy, P.E.
Phone: (360) 778-7909
Email: jamalloy@cob.org

Participating Departments