Northwest/Bakerview Intersection Improvements

​​​​​​​​​​​​​​Project Overview: ES-0546

 

This project will evaluate and improve pedestrian and bicycle safety and efficiency through the reconstruction of curb ramps, sidewalk, traffic islands, and installation of improved visibility pavement markings in the vicinity of the Northwest Avenue and West Bakerview Road intersection. It also involves evaluating and adding center median along West Bakerview Road from Arctic Avenue vicinity to Northwest Avenue vicinity. The purpose of these changes is to improve vehicular, pedestrian, and bicycle safety. 

Funding source: Transportation Benefit District Fund​​

Status – September 2020

Accomplishments

  • Northwest/Bakerview Mult​i-Agency Intersection Safety Study – Completed 2017
  • Advertised and selected H.W. Lochner, Inc. as design consultant. 
  • Design Complete. 
  • July 14, 2020 – Project Advertised. 
  • August 6, 2020 – Bids Opened with Granite Construction as the apparent low bidder at $374,656.00.​
  • August 24, 2020 – Council Award. 

Next Milestones: Construction. ​

Project Details

Contacts


Larry Scholten, P.E.
Project Engineer
Phone:  (360) 778​-7923

Chris Comeau
Transportation Planner
(360) 778-7946
ccomeau@cob.org

Participating Departments

Affected Neighborhoods