Description
Squalicum Creek Park Phase 4 includes a new ball field/multi-purpose sport field, related backstop, dug outs and paving. The project also includes a low-impact infiltration basin.
Status & Project Schedule
Closed. Depending on weather the new sport facility may be open for use in Spring 2023.
Design Phase Completed
Bid Phase Completed
Construction Phase Completed
Phase 4 Budget & Funding Source
• Budget: $1.25 million
• Funding Source: Washington State Recreation and Conservation Office Youth Athletic Facility (YAF) Grant, Greenways Levy funds, and Park Impact Fees
Contractor & Consultants
City’s Project Manager: Jonathan Schilk, RLA
Design Consultants:
RW Droll Landscape Architect, PS
Reichhardt & Ebe Engineering, Inc.
GeoEngineers, Inc.
Stantec, Inc.
Contractor: Fabor Construction Company, Inc.