Squalicum Creek Park Phase 4 includes a new ball field/multi-purpose sport field, related backstop, dug outs and paving. The project also includes a low-impact infiltration basin.
Status & Project Schedule
Active. RW Droll Landscape Architect, PS, has been hired to design the new sport facility.
Design Phase now – end of March 2020
Permits now – mid April 2020
Bid Phase mid April – mid May 2020
Construction Phase mid June – mid October 2020
Phase 4 Budget & Funding Source
• Budget: $1.25 million
• Funding Source: State Youth Athletic Facility (YAF) Grant, Greenway 3 Levy and Park Impact Fees
Contractor & Consultants
City’s Project Manager: Jonathan Schilk, RLA
Design Consultants:
RW Droll Landscape Architect, PS
Reichhardt & Ebe Engineering, Inc.
GeoEngineers, Inc.
Stantec, Inc.
Contractor: TBD