Project Overview: EN053
This project included the design and construction of stream bank and channel stabilization features along West Cemetery Creek. This project installed natural bed and bank features, facilitated stormwater dispersion along the creek, and reduced sediment loads to improve water quality and restore natural processes in West Cemetery Creek and downstream water bodies.
Funding for this project came from a Washington State Department of Ecology Centennial Clean Water Program grant.
For project background information please see the West Cemetery Creek Water Quality Improvements webpage.
Project Details
- Status – Construction complete
- Contract awarded – July 12, 2021
- Contract amount – $608,103.84
- Contractor – Henifin Construction
- Vicinity Map
Contact
Freeman Anthony, P.E.
Project Engineer
Phone: (360) 778-7924