Turning clocks back one hour will make it darker earlier affecting travel during peak hours. Capital construction and maintenance projects will also continue to affect traffic. Due to continued threat of COVID-19, City construction work will be assessed on a day-by-day basis. As always, please pay attention to Health Department recommendations and travel with care.
Harrison Street Slope Stabilization
Work efforts continue to repair the existing water main, lower and modify the existing stormwater pond, regrade the steep slope, which is exhibiting slippage failure, install a block wall to replace the failing rockery wall, and provide plantings on the slope. The project is scheduled to be complete by the end of October to early November. For more information visit the Harrison Street Slope Stabilization Project website or contact Aric Smathers, P.E., project engineer, at arsmathers@cob.org or (360) 778-7942.
Northwest/Bakerview Intersection Improvements
Substantial delays should be expected, and people are encouraged to avoid the area if possible. The NW/Bakerview intersection project will improve pedestrian and bicycle safety and efficiency through the reconstruction of curb ramps, sidewalk, traffic islands, and installation of improved visibility pavement markings in the vicinity of the Northwest Avenue and West Bakerview Road intersection. A center median curb will also be installed along West Bakerview Road from Arctic Avenue vicinity to Northwest Avenue vicinity. Flaggers and traffic control will be present. For more information, visit the Northwest/Bakerview Intersection Improvements website or contact Larry Scholten, P.E., project engineer, at ljscholten@cob.org or (360) 778-7923.
Samish Maple Ellis Multimodal Safety Improvements
The Samish Maple Ellis Multimodal Safety Improvements project is wrapping up with site restoration and pavement marking throughout the corridor. Minor work near I-5 and other areas may be encountered. Flaggers will allow for local access and direct travelers to area detours. For more information, visit the Samish-Maple-Ellis Multimodal Safety Improvements website or contact Freeman (Fritz) Anthony, P.E., project engineer, at fanthony@cob.org or (360) 778-7924.
Sehome Hill Communications Tower – Antenna Installation/Tower Demo (pictured)
Work efforts continue to install the remaining antennas on the new communications tower, remove equipment from the old tower and demolish the old tower and building. The demolition and restoration portion of the project has begun. During this portion of the project, the upper parking lot will be closed as needed to allow space for equipment to perform the work for a period of two-three weeks. Road Closed signs and barricades will be placed at the bottom of the hill near the gate. As the tunnel trail is currently closed due to rocks falling within the tunnel, no other trail closures are anticipated for the remainder of the project. For more information visit the Sehome Hill Communications Tower – Antenna Installation Tower/Demo Project website or contact Aric Smathers, P.E., project engineer, at arsmathers@cob.org or (360) 778-7942.
2020 TBD Projects and 40th Street Sidewalk
The 40th Street Sidewalk and 2020 TBD Projects are wrapping up with minor restoration and striping work throughout town. Flaggers will allow for local access. Expect possible project related delays when traveling through these project sites. For more information, visit the 2020 TBD Projects and 40th Street Sidewalk website or contact Freeman (Fritz) Anthony, P.E., project engineer, at fanthony@cob.org or (360) 778-7924.
2020 Watermain Replacement project
The 2020 Watermain Replacement project will replace a watermain on Donovan Avenue from Connelly Creek to 36th Street, and on 35th Street from Donovan Avenue to one block north. Watermain installation will begin at Connelly Creek and move eastward. The affected blocks will be closed to through traffic. WTA is being coordinated with for impacts between 30th and 32nd Streets. Flaggers will allow for local access. Expect detours for affected closures. For more information, visit the 2020 Watermain Replacement Project website or contact Craig Mueller, P.E., project engineer, at camueller@cob.org or (360) 778-7922.
Meridian Street Water Quality Improvements
The Meridian St. water quality project on Meridian Street (State Route 539) between Bakerview Road and Stuart Road and on Kellogg Road will install 17 water quality devices to treat roadway runoff. This work will occur at night between 7 PM and 7 AM, Monday through Friday. The roadway will remain open with lane closures and lane shifts in place to facilitate construction. Flaggers will be present to provide additional traffic and pedestrian control as necessary. For more information, visit the Meridian Street Water Quality Improvements website or contact Larry Scholten, P.E., project engineer, at ljscholten@cob.org or (360) 778-7923.
West Horton project
The West Horton Road project is ongoing with site restoration, light pole installation, wall installation and related work. Expect possible delays when traveling near this project site. For more information, visit the West Horton Road phase 1 website or contact Freeman (Fritz) Anthony, P.E., project engineer, at fanthony@cob.org or (360) 778-7924
Washington State Department of Transportation (WSDOT)
Drivers can get real-time traffic information on their phone with the WSDOT traffic app, tracking the WSDOT north Twitter feed, and get advanced information from the WSDOT construction page.
Whatcom County
For updates on County projects near Bellingham, visit http://www.co.whatcom.wa.us/308/Public-Works. Subscribe to Whatcom County Public Works email newsletter here.
We provide this “capital project report” as a public service based on currently available information. When traveling through a construction area – whether walking, cycling or driving – please be patient, travel with care and always obey flaggers. In dark conditions, please make sure you’re visible to others. Planned road closures and restrictions are necessary to allow for a variety of work including resurfacing, sidewalk construction, water and sewer main work, and utility cuts. Dates, times and work locations may vary, depending on inclement weather or last-minute changes in work schedules. Questions? Contact AskPW@cob.org.