Project Overview
This project is the third phase of a multi-phased approach to treat polluted runoff (stormwater) that enters Little Squalicum Creek from developed land in the Birchwood Neighborhood. The project will install stormwater treatment systems, such as bioretention or enhanced treatment Best Management Practice (BMP) systems, to treat approximately 145.5 acres of stormwater, improving water quality in Little Squalicum Creek.

Project Status – 2026
The project is currently in the middle stages of design. Design will continue through summer 2026, at which point we anticipate applying for grant funding. Construction is expected in spring/summer 2028, although this timeline is dependent on funding.
Sign up to receive monthly email updates on current Public Works projects and programs.
More Information
Contact
General project questions: AskPW@cob.org
Media inquiries: pwmedia@cob.org
Project Engineer
Kyle Carlson, P.E.
Phone: (360) 778-7946
Email: kmcarlson@cob.org