Annual Sanitary Sewer Rehabilitation Project

​​Project Overview: ​EU-0178

Annual program for replacement and rehabilitation of sanitary sewer mains and manholes via open-trench and trenchless methods. This project will rehabilitate or replace sewer mains and manholes which are deteriorated or have reached the end of their service life. The program also includes elements to reduce or eliminate stormwater inflow and groundwater infiltration into the sanitary sewer system, reducing flow volumes to the City’s Waste Water Treatment Plant.

Funding from the City Sewer Fund.

​Status – February 2021

Accomplishments:​ The project is complete.

Next Milestone: ​Warranty period.

Project Details

  • Status – Warranty period
  • Contract Awarded – 2/10/2020
  • Contract Amount – $1,595,621.43
  • Contractor – Faber Construction
  • Completion Date – October 4, 2020
  • Final Contract Amount – $1,864,025.44
  • Vicinity Map​​

Contacts

​Aric Smathers, P.E.
Project Engineer
Phone: ​(360) 7​78-7942​​​​
Public Wor​ks Contacts​​

Participating Departments

Affected Neighborhoods