Project Overview: EW238
This project will replace the following utilities within the Valencia Street corridor:
- 3,900 linear feet of 12″ watermain
- 1,900 linear feet of 48″ storm main
- 1,200 linear feet of 8″ sewer line
Following the utility replacements, the corridor roadway will have hardscape replaced and upgraded as needed, as well as a full overlay. The purpose of this project is to provide required maintenance of existing utilities to ensure reliability.

Funding for this project is from the Water fund, Sewer fund, Stormwater fund, and Transportation fund.
Status – March 2023
Accomplishments: Completed permitting and project design.
Next Milestones: Bid, award, and contract the project.
Project Details
- Status – Design (100%)
- Contract awarded –
- Contract amount –
- Contractor –
Contacts
Freeman (Fritz) Anthony, PE
Project Engineer
(360) 778-7924
fanthony@cob.org