Holly Street Multimodal Improvements (Broadway to Champion Street)

The City of Bellingham is planning to complete multimodal improvements along W. Holly Street between Broadway and W. Champion Street. The Holly Street Multimodal Improvements Project (ES601) will fill key network gaps and address high-priority projects from the 2024 Pedestrian Master Plan and Bike Master Plan. The project will create safer, more comfortable crossings, add lighting, and improve accessibility for people walking and rolling. It will also provide a continuous, separated bike facility designed for riders of all ages and abilities, filling a critical gap within the city’s bike network.

This project does not include any planned changes to existing multimodal infrastructure between Ellis Street and Bay Street. We are evaluating long‑term options for the bike lanes in this area through the Downtown Connections Project.

Project Overview

The Holly Street Multimodal Improvements Project from Broadway to Champion is a direct result of the Holly Street Corridor Study. The study examined the entire roadway between Ellis Street and Broadway to identify preferred designs that advance our long‑term vision for safer and more comfortable pedestrian and bike facilities along the corridor. Guided by community input and staff recommendations, this project will construct multimodal facilities along Holly Street between West Champion Street and Broadway, focusing on locations without existing bike facilities to close network gaps, improve safety at key locations, and enable phased upgrades over time. For study details on evaluated alternatives, you can review the Holly Street Corridor Alternatives Study Final Report.

Proposed Concepts for Multimodal Improvements between Broadway and Champion

The graphics below show two example illustrations of the proposed improvements on Holly Street. The first graphic represents the proposed enhancements between West Champion Street and C Street, near Maritime Heritage Park. This part of the corridor has more space in the right‑of‑way, which allows us to keep some on‑street parking and provide wider sidewalks.

The second graphic shows the section between C Street and Broadway. Because the right‑of‑way is narrower here, we propose removing parking on both sides of the street. This is necessary to provide continuous facilities for people walking and biking throughout the corridor. To help offset the reduction of street parking on this section of Holly Street, we’ve recently expanded dedicated street parking throughout Old Town.

Cross section of selected design for Holly Street multimodal improvements planned along the Whatcom Creek section of the roadway.
Cross section of selected design for Holly Street multimodal improvements planned along the West End section of the roadway.

Project Status Fall 2026

The team has developed a 10% design roll plot for the project and is preparing to seek approval from the Transportation Commission and City Council for street parking removals necessary to support project implementation.

More Information

  • Corridor Study: Concluded summer 2026 – filling infrastructure gap between Broadway and Champion selected as near-term capital project.
  • Contractor: TBD
  • Tentative Schedule:
    • 30-60% design Open House: Spring 2027
    • Expected construction start date: 2028

From August through September 2025, the City gathered community input on corridor priorities through an Engage Bellingham campaign. This feedback directly informed the City’s decision to move forward with a near-term capital project to fill a key gap on Holly Street between Champion and Broadway, where no bike facilities currently exist. You can review community questions and answers on the Engage Bellingham Holly Street Corridor Study page. The City will announce additional opportunities for public input early in the design process.

This project is shown as fully funded in the 2027-2032 Transportation Improvement Program (TIP). Funding for this project comes from the Transportation Fund (non-motorized) and Transportation Impact Fees.

Vicinity map showing project boundaries along Holly Street between Broadway and Champion Street

Transportation Data

An engineering evaluation of existing roadway conditions in 2016 identified a high level of traffic stress for bicyclists along this stretch of Holly Street. This indicates a functional gap in the active transportation network that poses systemic safety risks, likely deterring all but the most confident riders. Despite these challenges, data shows that bicyclists make up approximately 3.6% of total traffic during the afternoon peak hour, underscoring the importance of this corridor in the city’s bike network.  

City’s Commitment to Improving Multimodal Transportation Options

For more than 15 years, downtown Bellingham has steadily expanded active transportation facilities, adding bike lanes to most downtown arterials. However, Holly Street remained a notable exception until the 2024 bike lane pilot project began addressing this gap. 

2024 Holly Street Bike Lane Pilot Project

The 2024 Holly Street Bike Lane Pilot Project reaffirmed Holly Street’s significance as downtown Bellingham’s busiest bike corridor, with ridership surpassing the next highest route by more than 44% between June and September 2024. Findings from the Pilot highlight the need for improved bicycle facilities along this corridor to support the city’s overarching multimodal transportation goals. You can find more information about the pilot project on the Holly Street Bike Lane Pilot Project webpage.

Contact

General project questions: AskPW@cob.org

Media inquiries: pwmedia@cob.org

Project Engineer
Aric Smathers, PE
Phone: (360) 778-7942
arsmathers@cob.org

Participating Departments

Affected Neighborhoods

Similar Projects by Topic

Our public calendar is being upgraded and may be unavailable for periods of time on Friday, Jun 19.

Secret Link