Mill Avenue Overlay

Project Overview: ES-556

This project involves installing sidewalks, curb, and gutter on both sides and then overlaying Mill Street from Samish Way to 40th Street to improve pedestrian access and preserve roadway services. The project includes site survey and geotech investigation as needed. Construction scope includes addition of street section, stormwater improvements and site restoration. Challenges include steep grades and working around existing features. Some traffic impacts to Samish Way, as well as Mill Avenue.

Funding source: Transportation Fund

Status – July 2022

Accomplishments: Stormwater system and curb, gutter, and sidewalk installed.

Next milestones: Pedestrian connection to Samish Way, paving, and site restoration.

Project Details

  • Status – Construction
  • Contract awarded – 2/7/2022
  • Contract amount – $1,173,445.98
  • Contractor – Tiger Construction
  • Vicinity​ M​​ap

Contacts

Freeman (Fritz) Anthony, PE
Project Engineer
(360) 778-7924
fanthony@cob.org

Participating Departments

Affected Neighborhoods

Similar Projects by Topic