Project Overview: ES-556
This project involves installing sidewalks, curb, and gutter on both sides and then overlaying Mill Street from Samish Way to 40th Street to improve pedestrian access and preserve roadway services. The project includes site survey and geotech investigation as needed. Construction scope includes addition of street section, stormwater improvements and site restoration. Challenges include steep grades and working around existing features. Some traffic impacts to Samish Way, as well as Mill Avenue.
Funding source: Transportation Fund
Status – July 2022
Accomplishments: Stormwater system and curb, gutter, and sidewalk installed.
Next milestones: Pedestrian connection to Samish Way, paving, and site restoration.
Project Details
- Status – Construction
- Contract awarded – 2/7/2022
- Contract amount – $1,173,445.98
- Contractor – Tiger Construction
- Vicinity Map
Contacts
Freeman (Fritz) Anthony, PE
Project Engineer
(360) 778-7924
fanthony@cob.org