Mill Avenue Overlay

Project Overview: ES-556

This project involves installing sidewalks, curb, and gutter on both sides and then overlaying Mill Street from Samish Way to 40th Street to improve pedestrian access and preserve roadway services. The project includes site survey and geotech investigation as needed. Construction scope includes addition of street section, stormwater improvements and site restoration. Challenges include steep grades and working around existing features. Some traffic impacts to Samish Way, as well as Mill Avenue.

Funding source: Transportation Fund

Status – December 2022

Accomplishments: Project substantially complete.

Next milestones: Close-out work including punchlist items, such as pedestrian ramp handrail due for installation before the end of the year.

Project Details

  • Status – Construction
  • Contract awarded – 2/7/2022
  • Contract amount – $1,173,445.98
  • Contractor – Tiger Construction
  • Vicinity​ M​​ap

Contacts

Freeman (Fritz) Anthony, PE
Project Engineer
(360) 778-7924