Lincoln Street / E Maple Street Traffic Signal

Aerial view of the intersection at East Maple and Lincoln
Project Overview: ET034 This project includes constructing a full traffic signal at Lincoln/E Maple to improve intersection operation and break the 0.86-mile corridor in half by providing a protected pedestrian crossing. The signal will be one of several planned improvements on this corridor to enhance safety for drivers, pedestrians, bicyclists, and transit users (See Project ... Read more

Bellingham Sportsplex HVAC, Roof & Energy Upgrades

This project includes building upgrades to the Bellingham Sportsplex Building. This is one of the largest recreational buildings in the city’s system. Activities at the Sportsplex include hockey, indoor soccer, speed skating, events, day camps, and other uses. Constructed in the early 2000’s, the existing heating, ventilation, and roof system need replacement. This project will ... Read more

Woburn, Yew, Electric, and Newmarket Sanitary Sewer Main Replacement

Project Overview: EU190 This project will replace sewer mains in Woburn St. from Fraser St. south, Woburn St. from Texas St. to E. Illinois St. vicinity, Newmarket St. from Woburn St. to Barkley Blvd., Yew St. from Carolina St. to Texas St., and Electric Ave. from Arbor St. north. This project is funded by City ... Read more

Gardenview Tiny House Village Project

Project Description The City will host a new tiny house village at 1399 Woburn Street, the former site of the City’s “Clean Green” facility. More information can be found in the July 22, 2021 and the February 24, 2021 press releases. The City of Bellingham sought a partnership with qualified providers through a Request for ... Read more

Whatcom Creek Trunk Main

​​​​​​​​​​​Project Overview: EU182 This project will re-line a 1909 sewer trunk main along Whatcom Creek from Nevada R/W West to the State/York intersection. The goal of the project is to extend the life of the egg-shaped pipe by re-lining the interior. Videos of the interior of the main shows deterioration in the pipe including holes ... Read more

West Cemetery Creek Water Quality Project

Stream in a forest
​​​​​​​​​​​Project Overview: EN05​3 ​​This project includes the design and construction of stream bank and channel stabilization features along West Cemetery Creek. This project will install natural bed and bank features, facilitate stormwater dispersion along the creek, and reduce sediment loads to improve water quality and restore natural processes in West Cemetery Creek and downstream water bodies.  ... Read more